Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
015901039 |
TxDOT District |
San Angelo |
County Name |
Tom Green |
Funding Status |
Funded |
| Highway |
US 277 |
Project Length |
6.010 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Jul |
| Work From |
0.97 MILES SOUTH OF US 87 |
Low Bid Amount |
$2,734,302.86 |
| Work To |
7 MILES SOUTH OF US 87 |
| Description |
CONSTRUCT MERGE LANES |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Gary Enos, P.E. |
Phone: |
(325) 947-9233 |
| Construction Company |
REECE ALBERT, INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
07/2011 |
09/2011 |
09/2011 |
03/2012 |
03/2012 |
03/2012 |
|
03/2012 |
| Actual Date |
07/2011 |
09/2011 |
10/2011 |
04/2012 |
05/2012 |
04/2012 |
|
05/2012 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 09/24/2012 |
01/02/2013 |
182 |
67 |
36.81 % |
39.79 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$27,343.02 |
$112,414.08 |
| Construction |
$2,373,079.63 |
$999,396.59 |
Construction Engineering |
$134,527.70 |
$55,051.51 |
Contingency
 |
$28,163.32 |
|
Indirect
 |
$350,811.06 |
|
| Total Cost |
$2,913,924.73 |
$1,166,862.18 |
|
 |