Proposition 12 v2 Project Detail

Data updated on: 11/10/2014 3:25 PM Print This Page
Project Summary
Project ID 015802062 TxDOT District San Angelo County Name Tom Green Funding Status Funded
Highway US 67 Project Length .559 Miles Project Type Proposition 12 v2 Bid Date 2012-Aug
Work From AT US 277 Low Bid Amount $5,288,891.02
Work To .
Description REPLACE BRIDGE
Show Project Location
Contact Information
TxDOT Contact Gary Enos, P.E. Phone: (325) 947-9233
Construction Company JASIRI CONSTRUCTION, L.L.C.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
10/24/2012 01/07/2013 378 392 102.35 % 56.71 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $259,155.66 $0.00
Construction $5,150,060.80 $0.00
Construction EngineeringConstruction Engineering Definition $394,022.38 $0.00
Contingency Contingency Definition NaN
Indirect Indirect Definition $678,564.72
Total Cost $6,481,803.56 $0.00