Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
015606039 |
TxDOT District |
Wichita Falls |
County Name |
Baylor |
Funding Status |
Funded |
| Highway |
US 277 |
Project Length |
5.896 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Jun |
| Work From |
2.78 MILES EAST OF RM 1919 |
Low Bid Amount |
$10,550,963.24 |
| Work To |
0.64 MILES EAST OF US 183/283 |
| Description |
CONSTRUCT NEW ROADWAY LANES |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Danny Brown, P.E. |
Phone: |
(940) 720-7740 |
| Construction Company |
A. L. HELMCAMP, INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
10/2011 |
10/2011 |
12/2011 |
01/2012 |
01/2012 |
01/2012 |
05/2012 |
05/2012 |
| Actual Date |
10/2011 |
10/2011 |
12/2011 |
01/2012 |
03/2012 |
03/2012 |
11/2011 |
03/2012 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 08/20/2012 |
09/10/2012 |
269 |
144 |
51.61 % |
49.72 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$516,997.20 |
$525,206.35 |
| Construction |
$8,857,829.35 |
$5,565,300.04 |
Construction Engineering |
$523,327.78 |
$146,369.03 |
Contingency
 |
$209,964.17 |
|
Indirect
 |
$1,017,112.86 |
|
| Total Cost |
$11,125,231.36 |
$6,236,875.42 |
|
 |