Proposition 12 v2 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 015105097 TxDOT District Austin County Name Williamson Funding Status Funded
Highway US 183 Project Length .100 Miles Project Type Proposition 12 v2 Bid Date 2013-Aug
Work From AT NEW HOPE DRIVE Low Bid Amount $529,532.04
Work To .
Description WIDEN ROADWAY
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Walter Barfield, P.E. Phone: (512) 832-7136
Construction Company BPI ENVIRONMENTAL SERVICES INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
11/20/2013 67 35 52.24 % 59.98 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $25,947.07 $19,728.52
Construction $464,875.00 $189,664.48
Construction EngineeringConstruction Engineering Definition $33,784.14 $26,419.53
Contingency Contingency Definition $6,830.96
Indirect Indirect Definition $30,659.91
Total Cost $562,097.08 $235,812.53