Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
013603044 |
TxDOT District |
Paris |
County Name |
Delta |
Funding Status |
Funded |
| Highway |
SH 24 |
Project Length |
10.818 Miles |
Project Type |
Proposition 12 v2 |
District Est. Bid Date |
2013-Aug |
| Work From |
FM 904 |
|
|
| Work To |
FM 64 |
| Description |
CONSTRUCT NEW ROADWAY LANES |
| Project Note |
This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources. |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Rick Mackey, P.E. |
Phone: |
(903) 737-9375 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
04/2012 |
12/2012 |
01/2013 |
05/2013 |
01/2012 |
08/2014 |
06/2014 |
05/2013 |
| Actual Date |
04/2012 |
11/2012 |
02/2013 |
|
01/2012 |
|
|
|
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$1,683,397.87 |
$2,956,706.77 |
| Construction |
$34,355,058.59 |
$0.00 |
Construction Engineering |
$2,233,078.81 |
$0.00 |
Contingency
 |
$2,404,854.11 |
|
Indirect
 |
$1,724,623.94 |
|
| Total Cost |
$42,401,013.32 |
$2,956,706.77 |
|
 |