Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 013301043 TxDOT District Childress County Name King Funding Status Funded
Highway US 82 Project Length 18.938 Miles Project Type Proposition 12 v2 Bid Date 2012-Jun
Work From 1 MILE E OF US 83, E Low Bid Amount $9,739,695.34
Work To KNOX C/L
Description RESURFACE ROADWAY
Show Project Location
Contact Information
TxDOT Contact Chuck Steed, P.E. Phone: (940)-937-7191
Construction Company RK HALL, LLC
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
08/10/2012 04/01/2013 167 15 8.98 % 8.17 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $477,245.07 $57,145.53
Construction $8,996,964.16 $836,455.15
Construction EngineeringConstruction Engineering Definition $483,088.89 $31,725.26
Contingency Contingency Definition $193,819.94
Indirect Indirect Definition $1,302,197.27
Total Cost $11,453,315.33 $925,325.94