Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
011406030 |
TxDOT District |
Austin |
County Name |
Bastrop |
Funding Status |
Funded |
| Highway |
US 290 |
Project Length |
5.566 Miles |
Project Type |
Proposition 12 v2 |
District Est. Bid Date |
2013-Aug |
| Work From |
8.864 MI E OF FM 696 |
|
|
| Work To |
FM 2104 |
| Description |
WIDEN AND REHABILITATE ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Walter Barfield, P.E. |
Phone: |
(512) 832-7136 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
01/2009 |
07/2009 |
02/2010 |
08/2012 |
12/2011 |
08/2012 |
02/2012 |
08/2012 |
| Actual Date |
01/2009 |
07/2009 |
02/2010 |
|
12/2011 |
|
|
|
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$1,092,043.14 |
$593,267.45 |
| Construction |
$22,286,594.74 |
$0.00 |
Construction Engineering |
$1,105,415.10 |
$0.00 |
Contingency
 |
$443,503.24 |
|
Indirect
 |
$1,290,393.84 |
|
| Total Cost |
$26,217,950.06 |
$593,267.45 |
|
 |