Proposition 12 v2 Project Detail

Data updated on: 12/02/2014 8:49 AM Print This Page
Project Summary
Project ID 011402096 TxDOT District Austin County Name Travis Funding Status Funded
Highway US 290 Project Length .365 Miles Project Type Proposition 12 v2 Bid Date 2013-Aug
Work From RIATA TRAIL Low Bid Amount $2,844,477.38
Work To LEXINGTON STREET
Description CONSTRUCT INTERSECTION IMPROVEMENTS
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Walter Barfield, P.E. Phone: (512) 832-7136
Construction Company CAPITAL EXCAVATION COMPANY
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
01/06/2014 02/10/2014 139 135 97.12 % 97.92 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $127,434.99 $433,121.59
Construction $2,163,248.73 $1,535,434.21
Construction EngineeringConstruction Engineering Definition $119,645.27 $99,317.50
Contingency Contingency Definition $9,325.24
Indirect Indirect Definition $150,581.35
Total Cost $2,570,235.58 $2,067,873.30