Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 011402096 TxDOT District Austin County Name Travis Funding Status Funded
Highway US 290 Project Length .365 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Aug
Work From RIATA TRAIL
Work To LEXINGTON STREET
Description CONSTRUCT INTERSECTION IMPROVEMENTS
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Walter Barfield, P.E. Phone: (512) 832-7136
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 12/2011 07/2012 10/2012 05/2013 01/2013 03/2013 02/2013 05/2013
Actual Date 12/2011 06/2012 08/2012 10/2012
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $96,708.17 $404,354.72
Construction $1,973,636.23 $0.00
Construction EngineeringConstruction Engineering Definition $90,526.75 $0.00
Contingency Contingency Definition $6,273.38
Indirect Indirect Definition $114,273.54
Total Cost $2,281,418.07 $404,354.72