Proposition 12 v2 Project Detail

Data updated on: 10/01/2014 8:23 AM Print This Page
Project Summary
Project ID 011302060 TxDOT District Austin County Name Gillespie Funding Status Funded
Highway US 290 Project Length 3.000 Miles Project Type Proposition 12 v2 Bid Date 2013-Jun
Work From DUSTY FARM LANE Low Bid Amount $3,199,721.67
Work To JUNG LN E OF BLUMENTHAL
Description CONSTRUCT CENTER TURN LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Walter Barfield, P.E. Phone: (512) 832-7136
Construction Company ALLEN KELLER COMPANY
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
08/26/2013 09/03/2013 125 139 108.59 % 105.13 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $156,786.36 $406,440.86
Construction $3,027,364.46 $3,704,174.16
Construction EngineeringConstruction Engineering Definition $156,786.36 $89,722.76
Contingency Contingency Definition $1,599.86
Indirect Indirect Definition $185,263.88
Total Cost $3,527,800.92 $4,200,337.78