Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
011302060 |
TxDOT District |
Austin |
County Name |
Gillespie |
Funding Status |
Funded |
| Highway |
US 290 |
Project Length |
3.000 Miles |
Project Type |
Proposition 12 v2 |
District Est. Bid Date |
2013-Jun |
| Work From |
DUSTY FARM LANE |
|
|
| Work To |
JUNG LN E OF BLUMENTHAL |
| Description |
CONSTRUCT CENTER TURN LANES |
| Project Note |
This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources. |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Walter Barfield, P.E. |
Phone: |
(512) 832-7136 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
01/2012 |
05/2012 |
08/2012 |
01/2013 |
03/2013 |
12/2012 |
|
03/2013 |
| Actual Date |
03/2012 |
05/2012 |
09/2012 |
03/2013 |
04/2013 |
04/2013 |
|
04/2013 |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$148,340.86 |
$388,726.03 |
| Construction |
$3,027,364.46 |
$0.00 |
Construction Engineering |
$148,340.86 |
$0.00 |
Contingency
 |
$1,513.68 |
|
Indirect
 |
$175,284.40 |
|
| Total Cost |
$3,500,844.26 |
$388,726.03 |
|
 |