Proposition 12 v2 Project Detail

Data updated on: 6/03/2013 7:32 AM Print This Page
Project Summary
Project ID 011302060 TxDOT District Austin County Name Gillespie Funding Status Funded
Highway US 290 Project Length 3.000 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Jun
Work From DUSTY FARM LANE
Work To JUNG LN E OF BLUMENTHAL
Description CONSTRUCT CENTER TURN LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Walter Barfield, P.E. Phone: (512) 832-7136
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 01/2012 05/2012 08/2012 01/2013 03/2013 12/2012 03/2013
Actual Date 03/2012 05/2012 09/2012 03/2013 04/2013 04/2013 04/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $148,340.86 $388,726.03
Construction $3,027,364.46 $0.00
Construction EngineeringConstruction Engineering Definition $148,340.86 $0.00
Contingency Contingency Definition $1,513.68
Indirect Indirect Definition $175,284.40
Total Cost $3,500,844.26 $388,726.03