Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 011109041 TxDOT District Houston County Name Brazoria Funding Status Funded
Highway BS 288B Project Length 1.386 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Jul
Work From WILKINS STREET
Work To HENDERSON STREET
Description INSTALL PAVEMENT STRIPES/MARKERS
Show Project Location
Contact Information
TxDOT Contact Bill Brudnick, P.E. Phone: (713) 802-5617
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 12/2011 12/2011 02/2012 02/2013 04/2013 04/2013 04/2013 04/2013
Actual Date 10/2011 12/2011 01/2013 04/2013 04/2013 04/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $20,791.09 $43,772.78
Construction $424,308.02 $0.00
Construction EngineeringConstruction Engineering Definition $27,070.85 $0.00
Contingency Contingency Definition $5,473.57
Indirect Indirect Definition $20,069.77
Total Cost $497,713.30 $43,772.78