Proposition 12 v2 Project Detail

Data updated on: 8/01/2014 2:38 PM Print This Page
Project Summary
Project ID 010805014 TxDOT District Tyler County Name Henderson Funding Status Funded
Highway SH 19 Project Length 4.636 Miles Project Type Proposition 12 v2 Bid Date 2012-Aug
Work From 4.1 MI N OF FM 837 (CR 468N), N Low Bid Amount $6,385,017.81
Work To 3.5 MI S OF FM 1615 (COON CRK BRG)
Description WIDEN ROADWAY
Show Project Location
Contact Information
TxDOT Contact Vernon Webb, P.E. Phone: (903) 510-9296
Construction Company APAC-TEXAS, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
10/18/2012 11/19/2012 265 280 105.66 % 92.37 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $312,865.87 $133,473.31
Construction $6,264,365.80 $6,297,271.64
Construction EngineeringConstruction Engineering Definition $638,501.78 $311,660.19
Contingency Contingency Definition $134,085.37
Indirect Indirect Definition $450,143.76
Total Cost $7,799,962.58 $6,742,405.14