Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
010805014 |
TxDOT District |
Tyler |
County Name |
Henderson |
Funding Status |
Funded |
| Highway |
SH 19 |
Project Length |
4.636 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Aug |
| Work From |
4.1 MI N OF FM 837 (CR 468N), N |
Low Bid Amount |
$6,385,017.81 |
| Work To |
3.5 MI S OF FM 1615 (COON CRK BRG) |
| Description |
WIDEN ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Vernon Webb, P.E. |
Phone: |
(903) 510-9296 |
| Construction Company |
APAC-TEXAS, INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
11/2011 |
03/2012 |
04/2012 |
05/2012 |
11/2011 |
05/2012 |
|
05/2012 |
| Actual Date |
11/2011 |
04/2012 |
04/2012 |
06/2012 |
11/2011 |
06/2012 |
|
06/2012 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 10/18/2012 |
11/19/2012 |
265 |
83 |
31.32 % |
20.62 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$312,865.87 |
$133,233.71 |
| Construction |
$6,264,365.80 |
$1,259,252.33 |
Construction Engineering |
$638,501.78 |
$65,297.94 |
Contingency
 |
$134,085.37 |
|
Indirect
 |
$450,143.76 |
|
| Total Cost |
$7,799,962.58 |
$1,457,783.98 |
|
 |