Project ID 010204095 TxDOT District Corpus Christi County Name Kleberg Funding Status Funded
Highway US 77 Project Length .798 Miles Project Type Proposition 12 v2 Bid Date 2012-Apr
Work From S. OF SH 141 Low Bid Amount $14,562,421.93
Work To N. OF FM 425
Description CONSTRUCT OVERPASS/UNDERPASS
Show Project Location
Contact Information
TxDOT Contact Paula Sales-Evans, P.E. Phone: (361) 808-2222
Construction Company BAY LTD.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
06/18/2012 10/24/2012 352 403 101.00 % 96.89 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $713,558.67 $460,733.61
Construction $13,978,421.37 $15,257,197.45
Construction EngineeringConstruction Engineering Definition $691,715.04 $506,333.56
Contingency Contingency Definition $401,922.85
Indirect Indirect Definition $1,170,818.72
Total Cost $16,956,436.65 $16,224,264.62