Proposition 12 v2 Project Detail

Data updated on: 11/10/2014 3:25 PM Print This Page
Project Summary
Project ID 010202095 TxDOT District Corpus Christi County Name Nueces Funding Status Funded
Highway US 77 Project Length 1.116 Miles Project Type Proposition 12 v2 Bid Date 2012-Jul
Work From SH 44 Low Bid Amount $11,246,983.52
Work To FM 892
Description CONSTRUCT NEW ROADWAY LANES
Show Project Location
Contact Information
TxDOT Contact Paula Sales-Evans, P.E. Phone: (361) 808-2222
Construction Company HAAS-ANDERSON CONSTRUCTION, LTD.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
09/13/2012 01/16/2013 319 332 101.22 % 65.05 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $551,102.19 $272,709.26
Construction $11,327,373.42 $7,648,892.67
Construction EngineeringConstruction Engineering Definition $534,231.72 $378,892.30
Contingency Contingency Definition $310,416.75
Indirect Indirect Definition $904,257.48
Total Cost $13,627,381.56 $8,300,494.23