Proposition 12 v2 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 010006059 TxDOT District Corpus Christi County Name Karnes Funding Status Funded
Highway US 181 Project Length 6.682 Miles Project Type Proposition 12 v2 Bid Date 2012-Dec
Work From 1.761 MI S. OF US 181-G Low Bid Amount $8,563,333.47
Work To KARNES/BEE COUNTY LINE
Description CONSTRUCT NEW ROADWAY LANES
Show Project Location
Contact Information
TxDOT Contact Paula Sales-Evans, P.E. Phone: (361) 808-2222
Construction Company HUNTER INDUSTRIES, LTD.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
02/22/2013 03/10/2013 173 204 89.87 % 57.72 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $419,603.34 $435,247.15
Construction $9,246,441.87 $5,640,213.28
Construction EngineeringConstruction Engineering Definition $424,741.34 $200,628.06
Contingency Contingency Definition $170,410.34
Indirect Indirect Definition $468,414.33
Total Cost $10,729,611.22 $6,276,088.49