Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
009805026 |
TxDOT District |
Childress |
County Name |
Knox |
Funding Status |
Funded |
| Highway |
SH 6 |
Project Length |
.937 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Aug |
| Work From |
@ BRAZOS RIVER |
Low Bid Amount |
$4,296,515.09 |
| Work To |
. |
| Description |
REPLACE BRIDGE |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Chuck Steed, P.E. |
Phone: |
(940)-937-7191 |
| Construction Company |
COPPELL CONSTRUCTION CO., INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
01/2010 |
02/2010 |
03/2010 |
05/2010 |
02/2010 |
08/2010 |
08/2010 |
08/2010 |
| Actual Date |
06/2011 |
09/2011 |
12/2011 |
05/2012 |
04/2012 |
04/2012 |
04/2012 |
05/2012 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 10/12/2012 |
12/31/2012 |
210 |
46 |
21.90 % |
40.62 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$210,529.24 |
$403,392.67 |
| Construction |
$3,469,111.06 |
$1,883,469.56 |
Construction Engineering |
$320,090.37 |
$69,553.45 |
Contingency
 |
NaN |
|
Indirect
 |
$574,444.07 |
|
| Total Cost |
$4,574,174.74 |
$2,356,415.68 |
|
 |