Project Summary
Project ID 009302015 TxDOT District Dallas County Name Navarro Funding Status Funded
Highway SH 14 Project Length .862 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Aug
Work From AT UP RR
Work To SOUTH OF RICHLAND
Description CONSTRUCT OVERPASS/UNDERPASS
Show Project Location
Contact Information
TxDOT Contact Mo Bur, P.E. Phone: (214) 320-6281
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 11/2011 08/2012 12/2012 05/2013 02/2013 05/2013 05/2013 05/2013
Actual Date 11/2011 05/2012 07/2012 04/2013 12/2012 04/2013 04/2013 04/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $420,448.21 $921,521.78
Construction $8,580,575.74 $0.00
Construction EngineeringConstruction Engineering Definition $547,440.73 $0.00
Contingency Contingency Definition $110,689.43
Indirect Indirect Definition $374,113.10
Total Cost $10,033,267.21 $921,521.78