Project ID 008616004 TxDOT District Laredo County Name Webb Funding Status Funded
Highway SL 20 Project Length 2.292 Miles Project Type Proposition 12 v2 Bid Date 2012-Aug
Work From MANGANA-HEIN ROAD Low Bid Amount $11,417,278.20
Work To CIELITO LINDO
Description WIDEN ROADWAY
Show Project Location
Contact Information
TxDOT Contact Tito Gonzalez, P.E. Phone: (956) 712-7487
Construction Company ANDERSON COLUMBIA CO., INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
10/18/2012 01/14/2013 351 371 97.38 % 74.69 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $559,446.63 $307,579.11
Construction $8,842,006.87 $8,951,252.12
Construction EngineeringConstruction Engineering Definition $566,297.00 $631,059.58
Contingency Contingency Definition $227,203.84
Indirect Indirect Definition $913,382.26
Total Cost $11,108,336.60 $9,889,890.81