Proposition 12 v2 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 008309030 TxDOT District Atlanta County Name Titus Funding Status Funded
Highway SH 11 Project Length .331 Miles Project Type Proposition 12 v2 Bid Date 2013-Jun
Work From AT FM 1735 INTERSECTION Low Bid Amount $205,525.50
Work To .
Description INSTALL LEFT TURN LANE AT INTERSECTION
Show Project Location
Contact Information
TxDOT Contact Dennis M. Beckham, P.E. Phone: (903) 799-1222
Construction Company H. H. HOWARD & SONS, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
09/26/2013 10/08/2013 40 11 27.50 % 67.87 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $10,070.75 $100,589.13
Construction $202,692.75 $150,452.75
Construction EngineeringConstruction Engineering Definition $13,112.53 $21,542.35
Contingency Contingency Definition $2,651.28
Indirect Indirect Definition $11,776.61
Total Cost $240,303.92 $272,584.23