Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 008307040 TxDOT District Atlanta County Name Camp Funding Status Funded
Highway SH 11 Project Length .284 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-May
Work From AT FM 21 INTERSECTION
Work To .
Description INSTALL LEFT TURN LANE AT INTERSECTION
Show Project Location
Contact Information
TxDOT Contact Dennis M. Beckham, P.E. Phone: (903) 799-1222
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 03/2012 03/2012 04/2012 07/2012 04/2012 06/2012 06/2012 07/2012
Actual Date 02/2012 03/2012 04/2012 12/2012 10/2012 12/2012 12/2012 12/2012
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $13,495.02 $45,688.22
Construction $275,408.60 $0.00
Construction EngineeringConstruction Engineering Definition $17,571.07 $0.00
Contingency Contingency Definition $3,552.77
Indirect Indirect Definition $15,780.91
Total Cost $325,808.37 $45,688.22