Proposition 12 v2 Project Detail

Data updated on: 8/01/2014 2:38 PM Print This Page
Project Summary
Project ID 007214024 TxDOT District San Antonio County Name Kendall Funding Status Funded
Highway US 87 Project Length .238 Miles Project Type Proposition 12 v2 Bid Date 2012-Jul
Work From AT CIBOLO CREEK Low Bid Amount $943,105.78
Work To .
Description REPAIR BRIDGE
Show Project Location
Contact Information
TxDOT Contact Gregg Granato, P.E. Phone: (210) 615-6049
Construction Company RELMCO, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
08/21/2012 01/07/2013 166 318 175.69 % 92.38 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $46,212.18 $72,064.67
Construction $766,043.16 $934,033.57
Construction EngineeringConstruction Engineering Definition $71,393.11 $251,288.79
Contingency Contingency Definition $43,194.24
Indirect Indirect Definition $64,602.75
Total Cost $991,445.44 $1,257,387.03