Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
006805033 |
TxDOT District |
Lubbock |
County Name |
Dawson |
Funding Status |
Funded |
| Highway |
US 87 |
Project Length |
19.326 Miles |
Project Type |
Proposition 12 v2 |
District Est. Bid Date |
2013-May |
| Work From |
MARTIN COUNTY LINE |
|
|
| Work To |
SOUTH Y IN LAMESA |
| Description |
REPAIR ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Steve Warren, P.E. |
Phone: |
(806) 748-4490 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
05/2009 |
06/2009 |
07/2009 |
08/2009 |
08/2009 |
|
|
09/2009 |
| Actual Date |
06/2009 |
06/2009 |
07/2009 |
04/2010 |
02/2013 |
08/2009 |
08/2009 |
02/2013 |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$556,413.79 |
$40,329.88 |
| Construction |
$11,355,383.41 |
$0.00 |
Construction Engineering |
$556,413.79 |
$0.00 |
Contingency
 |
$5,677.69 |
|
Indirect
 |
$826,671.91 |
|
| Total Cost |
$13,300,560.59 |
$40,329.88 |
|
 |