Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
006801066 |
TxDOT District |
Lubbock |
County Name |
Lubbock |
Funding Status |
Funded |
| Highway |
US 87 |
Project Length |
1.181 Miles |
Project Type |
Proposition 12 v2 |
District Est. Bid Date |
2013-Jul |
| Work From |
700' NORTH OF N INTERSEC. OF LP 493 |
|
|
| Work To |
300' SOUTH OF S INTERSEC. OF LP 493 |
| Description |
CONSTRUCT INTERCHANGE |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Steve Warren, P.E. |
Phone: |
(806) 748-4490 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
|
|
|
|
|
|
|
|
| Actual Date |
01/2012 |
11/2012 |
03/2013 |
04/2013 |
03/2013 |
04/2013 |
04/2013 |
04/2013 |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$477,442.01 |
$235,792.70 |
| Construction |
$9,743,714.45 |
$0.00 |
Construction Engineering |
$456,980.21 |
$0.00 |
Contingency
 |
$291,337.06 |
|
Indirect
 |
$709,342.41 |
|
| Total Cost |
$11,678,816.14 |
$235,792.70 |
|
 |