Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 006801066 TxDOT District Lubbock County Name Lubbock Funding Status Funded
Highway US 87 Project Length 1.181 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Jul
Work From 700' NORTH OF N INTERSEC. OF LP 493
Work To 300' SOUTH OF S INTERSEC. OF LP 493
Description CONSTRUCT INTERCHANGE
Show Project Location
Contact Information
TxDOT Contact Steve Warren, P.E. Phone: (806) 748-4490
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date
Actual Date 01/2012 11/2012 03/2013 04/2013 03/2013 04/2013 04/2013 04/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $477,442.01 $235,792.70
Construction $9,743,714.45 $0.00
Construction EngineeringConstruction Engineering Definition $456,980.21 $0.00
Contingency Contingency Definition $291,337.06
Indirect Indirect Definition $709,342.41
Total Cost $11,678,816.14 $235,792.70