Proposition 12 v2 Project Detail

Data updated on: 12/02/2014 8:49 AM Print This Page
Project Summary
Project ID 006311055 TxDOT District Atlanta County Name Panola Funding Status Funded
Highway SH 149 Project Length .787 Miles Project Type Proposition 12 v2 Bid Date 2013-Jun
Work From 0.6 MI W OF FM 10 Low Bid Amount $1,796,137.06
Work To 0.2 MI E OF FM 10
Description INSTALL LEFT TURN LANE AT INTERSECTION
Show Project Location
Contact Information
TxDOT Contact Dennis M. Beckham, P.E. Phone: (903) 799-1222
Construction Company L. S. EQUIPMENT CO., INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
08/20/2013 03/11/2014 96 83 86.46 % 68.48 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $88,010.72 $73,486.13
Construction $1,569,711.50 $1,144,968.56
Construction EngineeringConstruction Engineering Definition $88,010.72 $64,624.59
Contingency Contingency Definition $898.07
Indirect Indirect Definition $102,918.65
Total Cost $1,849,549.66 $1,283,079.28