Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
006311055 |
TxDOT District |
Atlanta |
County Name |
Panola |
Funding Status |
Funded |
| Highway |
SH 149 |
Project Length |
.787 Miles |
Project Type |
Proposition 12 v2 |
District Est. Bid Date |
2013-Jun |
| Work From |
0.6 MI W OF FM 10 |
|
|
| Work To |
0.2 MI E OF FM 10 |
| Description |
INSTALL LEFT TURN LANE AT INTERSECTION |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Dennis M. Beckham, P.E. |
Phone: |
(903) 799-1222 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
08/2011 |
10/2012 |
11/2012 |
01/2013 |
03/2012 |
12/2012 |
|
02/2013 |
| Actual Date |
08/2011 |
10/2012 |
11/2012 |
02/2013 |
10/2012 |
02/2013 |
|
|
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$76,915.86 |
$72,728.46 |
| Construction |
$1,569,711.50 |
$0.00 |
Construction Engineering |
$76,915.86 |
$0.00 |
Contingency
 |
$784.86 |
|
Indirect
 |
$89,944.47 |
|
| Total Cost |
$1,814,272.55 |
$72,728.46 |
|
 |