Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
005407067 |
TxDOT District |
Brownwood |
County Name |
Brown |
Funding Status |
Funded |
| Highway |
US 84 |
Project Length |
1.485 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Jun |
| Work From |
NEAR TURTLE CREEK RD IN EARLY |
Low Bid Amount |
$3,919,576.36 |
| Work To |
FM 2126 |
| Description |
REPAIR ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Jason Scantling, P.E. |
Phone: |
(325)-643-0415 |
| Construction Company |
PRATER EQUIPMENT CO., INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
02/2010 |
03/2010 |
04/2010 |
07/2010 |
10/2010 |
10/2010 |
10/2010 |
10/2010 |
| Actual Date |
01/2010 |
07/2011 |
07/2011 |
03/2012 |
03/2012 |
03/2012 |
|
03/2012 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 08/16/2012 |
11/26/2012 |
293 |
109 |
37.20 % |
24.66 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$192,059.24 |
$172,522.72 |
| Construction |
$3,967,499.97 |
$1,037,079.39 |
Construction Engineering |
$192,982.33 |
$46,220.93 |
Contingency
 |
$2,733.18 |
|
Indirect
 |
$420,570.55 |
|
| Total Cost |
$4,775,845.27 |
$1,255,823.04 |
|
 |