Proposition 12 v2 Project Detail

Data updated on: 8/01/2014 2:38 PM Print This Page
Project Summary
Project ID 005009069 TxDOT District Houston County Name Harris Funding Status Funded
Highway US 290 Project Length 2.026 Miles Project Type Proposition 12 v2 Bid Date 2013-May
Work From WEST OF PINEMONT Low Bid Amount $142,790,300.34
Work To WEST OF 34TH STREET (SEGMENT 4)
Description CONSTRUCT NEW ROADWAY LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Pamela Elmer, P.E. Phone: (713) 802-5646
Construction Company OHL USA, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
07/10/2013 02/03/2014 1,008 144 14.29 % 13.81 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $5,810,644.50 $18,603,548.84
Construction $140,521,096.24 $21,150,077.93
Construction EngineeringConstruction Engineering Definition $5,711,612.02 $783,510.15
Contingency Contingency Definition $8,567,418.02
Indirect Indirect Definition $6,753,981.21
Total Cost $167,364,751.99 $40,537,136.92