Proposition 12 v2 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 005006081 TxDOT District Houston County Name Harris Funding Status Funded
Highway US 290 Project Length 4.962 Miles Project Type Proposition 12 v2 Bid Date 2013-Nov
Work From EAST OF MUESCHKE ROAD Low Bid Amount $85,215,953.75
Work To EAST OF TELGE ROAD (SEGMENT 9)
Description WIDEN ROADWAY
Show Project Location
Contact Information
TxDOT Contact Bill Brudnick, P.E. Phone: (713) 802-5617
Construction Company WILLIAMS BROTHERS CONSTRUCTION CO., INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
12/11/2013 02/11/2014 960 45 4.69 % 0.06 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $4,175,581.73 $3,587,905.77
Construction $94,520,145.25 $50,870.00
Construction EngineeringConstruction Engineering Definition $4,260,797.69 $5,894.08
Contingency Contingency Definition $153,388.72
Indirect Indirect Definition $4,115,930.57
Total Cost $107,225,843.96 $3,644,669.85