Proposition 12 v2 Project Detail

Data updated on: 12/02/2014 8:49 AM Print This Page
Project Summary
Project ID 004910003 TxDOT District Waco County Name McLennan Funding Status Funded
Highway LP 574 Project Length 1.002 Miles Project Type Proposition 12 v2 Bid Date 2013-Feb
Work From BU 77 Low Bid Amount $14,436,151.22
Work To IH 35
Description CONSTRUCT NEW ROADWAY LANES
Show Project Location
Contact Information
TxDOT Contact Andy Petter, P.E. Phone: (254) 867-2740
Construction Company THE LANE CONSTRUCTION CORPORATION
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
05/24/2013 06/04/2013 277 328 100.61 % 94.29 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $707,371.41 $504,358.73
Construction $12,203,542.77 $14,264,759.16
Construction EngineeringConstruction Engineering Definition $707,371.41 $354,556.79
Contingency Contingency Definition $180,451.89
Indirect Indirect Definition $626,528.96
Total Cost $14,425,266.44 $15,123,674.68