Project ID 004718068 TxDOT District Paris County Name Grayson Funding Status Funded
Highway US 75 Project Length .300 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Aug
Work From @ LOY LAKE ROAD (SHERMAN)
Work To .
Description WIDEN ROADWAY
Show Project Location
Contact Information
TxDOT Contact Rick Mackey, P.E. Phone: (903) 737-9375
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 08/2012 11/2012 12/2012 05/2013 12/2012 05/2013 05/2013 05/2013
Actual Date 08/2012 03/2013 04/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $288,659.00 $93,966.05
Construction $5,891,000.00 $0.00
Construction EngineeringConstruction Engineering Definition $292,193.60 $0.00
Contingency Contingency Definition $117,230.90
Indirect Indirect Definition $295,728.20