Proposition 12 v2 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 004718068 TxDOT District Paris County Name Grayson Funding Status Funded
Highway US 75 Project Length .434 Miles Project Type Proposition 12 v2 Bid Date 2013-Sep
Work From @ LOY LAKE ROAD (SHERMAN) Low Bid Amount $5,248,890.96
Work To .
Description WIDEN ROADWAY
Show Project Location
Contact Information
TxDOT Contact Rick Mackey, P.E. Phone: (903) 737-9375
Construction Company RAGLE CONSTRUCTION, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
01/06/2014 268 11 4.10 % 0.00 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $257,195.66 $213,928.79
Construction $5,930,878.44 $0.00
Construction EngineeringConstruction Engineering Definition $260,344.99 $8,914.08
Contingency Contingency Definition $104,452.93
Indirect Indirect Definition $253,521.43
Total Cost $6,806,393.45 $222,842.87