Proposition 12 v2 Project Detail

Data updated on: 12/02/2014 8:49 AM Print This Page
Project Summary
Project ID 004714068 TxDOT District Dallas County Name Collin Funding Status Funded
Highway US 75 Project Length 3.146 Miles Project Type Proposition 12 v2 Bid Date 2012-Aug
Work From TELEPHONE RD (CR 275) Low Bid Amount $63,579,301.83
Work To NORTH OF MELISSA ROAD
Description CONSTRUCT NEW ROADWAY LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Maher Ghanayem, P.E. Phone: (214) 320-6691
Construction Company ED BELL CONSTRUCTION COMPANY
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
11/16/2012 09/09/2013 920 356 38.07 % 41.71 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $3,115,385.79 $4,793,229.54
Construction $70,334,700.20 $22,671,559.45
Construction EngineeringConstruction Engineering Definition $2,733,909.98 $841,134.03
Contingency Contingency Definition $114,442.74
Indirect Indirect Definition $3,776,610.53
Total Cost $80,075,049.24 $28,305,923.02