Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
004519047 |
TxDOT District |
Paris |
County Name |
Grayson |
Funding Status |
Funded |
| Highway |
US 82 |
Project Length |
1.100 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Aug |
| Work From |
FM 1897 |
Low Bid Amount |
$26,059,261.46 |
| Work To |
FANNIN COUNTY LINE |
| Description |
WIDEN ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Rick Mackey, P.E. |
Phone: |
(903) 737-9375 |
| Construction Company |
D. L. LENNON INCORPORATED - CONTRACTOR |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
08/2011 |
10/2011 |
01/2012 |
05/2012 |
|
04/2012 |
04/2012 |
05/2012 |
| Actual Date |
08/2011 |
10/2011 |
01/2012 |
04/2012 |
|
05/2012 |
05/2012 |
04/2012 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 10/12/2012 |
11/15/2012 |
473 |
83 |
17.55 % |
16.80 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$1,276,903.81 |
$373,179.58 |
| Construction |
$26,082,107.19 |
$4,700,205.57 |
Construction Engineering |
$1,292,539.37 |
$77,946.73 |
Contingency
 |
$518,579.30 |
|
Indirect
 |
$2,126,435.73 |
|
| Total Cost |
$31,296,565.40 |
$5,151,331.88 |
|
 |