Project Summary
Project ID 004401094 TxDOT District Wichita Falls County Name Wichita Funding Status Funded
Highway US 82 Project Length 1.000 Miles Project Type Proposition 12 v2 Bid Date 2012-Jun
Work From US 82/287 UNDER WINDTHORST ROAD Low Bid Amount $2,692,739.05
Work To .
Description REPLACE BRIDGE
Show Project Location
Contact Information
TxDOT Contact Danny Brown, P.E. Phone: (940) 720-7740
Construction Company THE LANE CONSTRUCTION CORPORATION
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
07/31/2012 09/10/2012 220 219 99.55 % 102.29 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $131,944.21 $110,954.88
Construction $1,900,177.35 $2,992,358.23
Construction EngineeringConstruction Engineering Definition $203,840.35 $207,314.05
Contingency Contingency Definition $123,327.45
Indirect Indirect Definition $259,580.04
Total Cost $2,618,869.40 $3,310,627.16