Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
003917176 |
TxDOT District |
Pharr |
County Name |
Hidalgo |
Funding Status |
Funded |
| Highway |
US 83 |
Project Length |
.950 Miles |
Project Type |
Proposition 12 v2 |
District Est. Bid Date |
2013-Jul |
| Work From |
0.4 MI W OF INSPIRATION RD |
|
|
| Work To |
0.5 MI E OF INSPIRATION RD |
| Description |
WIDEN BRIDGE |
| Project Note |
This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources. |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Homero Bazan, P.E. |
Phone: |
(956) 702-6214 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
08/2011 |
12/2011 |
04/2012 |
10/2012 |
03/2012 |
11/2012 |
07/2012 |
11/2012 |
| Actual Date |
08/2011 |
12/2011 |
04/2012 |
|
03/2013 |
|
|
|
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$1,629,107.59 |
$112,759.17 |
| Construction |
$33,247,093.71 |
$0.00 |
Construction Engineering |
$3,324,709.37 |
$0.00 |
Contingency
 |
$994,088.10 |
|
Indirect
 |
$1,712,225.33 |
|
| Total Cost |
$40,907,224.10 |
$112,759.17 |
|
 |