Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 003917176 TxDOT District Pharr County Name Hidalgo Funding Status Funded
Highway US 83 Project Length .950 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Jul
Work From 0.4 MI W OF INSPIRATION RD
Work To 0.5 MI E OF INSPIRATION RD
Description WIDEN BRIDGE
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Homero Bazan, P.E. Phone: (956) 702-6214
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 08/2011 12/2011 04/2012 10/2012 03/2012 11/2012 07/2012 11/2012
Actual Date 08/2011 12/2011 04/2012 03/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,629,107.59 $112,759.17
Construction $33,247,093.71 $0.00
Construction EngineeringConstruction Engineering Definition $3,324,709.37 $0.00
Contingency Contingency Definition $994,088.10
Indirect Indirect Definition $1,712,225.33
Total Cost $40,907,224.10 $112,759.17