Proposition 12 v2 Project Detail

Data updated on: 11/10/2014 3:25 PM Print This Page
Project Summary
Project ID 003803033 TxDOT District Pharr County Name Zapata Funding Status Funded
Highway US 83 Project Length 5.442 Miles Project Type Proposition 12 v2 Bid Date 2012-Jun
Work From 1.50 MI N. OF FM 3169 Low Bid Amount $12,959,337.90
Work To 9.9 MI S. OF WEBB/ZAPATA CTY LINE
Description WIDEN AND REHABILITATE ROADWAY
Show Project Location
Contact Information
TxDOT Contact Homero Bazan, P.E. Phone: (956) 702-6214
Construction Company ANDERSON COLUMBIA CO., INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
08/10/2012 04/03/2013 378 397 105.03 % 93.20 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $635,007.56 $173,323.44
Construction $9,427,256.35 $12,787,130.23
Construction EngineeringConstruction Engineering Definition $642,783.16 $306,830.37
Contingency Contingency Definition $257,890.82
Indirect Indirect Definition $1,038,042.97
Total Cost $12,000,980.86 $13,267,284.04