Project ID 003706084 TxDOT District Laredo County Name Dimmit Funding Status Funded
Highway US 83 Project Length 10.134 Miles Project Type Proposition 12 v2 Bid Date 2012-Aug
Work From ASHERTON (SOUTH) CITY LIMITS Low Bid Amount $14,803,449.49
Work To 0.333 MI N OF FM 133
Description WIDEN AND REHABILITATE ROADWAY
Show Project Location
Contact Information
TxDOT Contact Tito Gonzalez, P.E. Phone: (956) 712-7487
Construction Company H. L. ZUMWALT CONSTRUCTION, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
10/24/2012 11/09/2012 282 345 97.46 % 88.42 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $725,369.03 $604,784.55
Construction $14,595,186.41 $13,724,667.14
Construction EngineeringConstruction Engineering Definition $725,369.03 $437,161.83
Contingency Contingency Definition $7,401.72
Indirect Indirect Definition $1,184,275.95
Total Cost $17,237,602.14 $14,766,613.52