Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 002814109 TxDOT District Beaumont County Name Orange Funding Status Funded
Highway IH 10 Project Length .100 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Jul
Work From AT SH 87 AND T&NO RR
Work To (STR 002814108 & 109)
Description REPLACE BRIDGE
Show Project Location
Contact Information
TxDOT Contact Phillip Lujan, P.E. Phone: (409) 898-5740
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date
Actual Date 10/2011
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $3,147,086.49 $1,089,963.14
Construction $64,226,255.05 $0.00
Construction EngineeringConstruction Engineering Definition $4,046,498.83 $0.00
Contingency Contingency Definition $1,314,882.64
Indirect Indirect Definition $3,686,587.04
Total Cost $76,421,310.05 $1,089,963.14