Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
002805042 |
TxDOT District |
Beaumont |
County Name |
Liberty |
Funding Status |
Funded |
| Highway |
US 90 |
Project Length |
5.440 Miles |
Project Type |
Proposition 12 v2 |
District Est. Bid Date |
2013-Jun |
| Work From |
SH 61 IN DEVERS |
|
|
| Work To |
4.0 MI W OF JEFFERSON CO. LINE |
| Description |
CONSTRUCT NEW ROADWAY LANES |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Phillip Lujan, P.E. |
Phone: |
(409) 898-5740 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
10/2010 |
06/2011 |
11/2011 |
08/2012 |
01/2012 |
05/2012 |
08/2012 |
08/2012 |
| Actual Date |
10/2010 |
01/2012 |
05/2012 |
|
|
|
|
|
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$844,344.85 |
$715,089.57 |
| Construction |
$17,231,527.62 |
$0.00 |
Construction Engineering |
$854,683.77 |
$0.00 |
Contingency
 |
$342,907.40 |
|
Indirect
 |
$989,089.69 |
|
| Total Cost |
$20,262,553.33 |
$715,089.57 |
|
 |