Proposition 12 v2 Project Detail

Data updated on: 9/02/2014 11:01AM Print This Page
Project Summary
Project ID 002805042 TxDOT District Beaumont County Name Liberty Funding Status Funded
Highway US 90 Project Length 5.440 Miles Project Type Proposition 12 v2 Bid Date 2013-Jun
Work From SH 61 IN DEVERS Low Bid Amount $20,677,586.39
Work To 4.0 MI W OF JEFFERSON CO. LINE
Description CONSTRUCT NEW ROADWAY LANES
Show Project Location
Contact Information
TxDOT Contact Phillip Lujan, P.E. Phone: (409) 898-5740
Construction Company APAC-TEXAS, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
09/11/2013 12/12/2013 540 120 22.22 % 16.90 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,013,201.73 $809,403.16
Construction $17,526,485.20 $3,646,535.93
Construction EngineeringConstruction Engineering Definition $1,025,608.28 $178,169.80
Contingency Contingency Definition $411,483.97
Indirect Indirect Definition $1,186,893.46
Total Cost $21,163,672.64 $4,634,108.89