Project ID 001705092 TxDOT District San Antonio County Name Medina Funding Status Funded
Highway IH 35 Project Length .733 Miles Project Type Proposition 12 v2 Bid Date 2013-Jul
Work From FM 3176 Low Bid Amount $1,564,899.84
Work To SH 173
Description CONSTRUCT FREEWAY RAMPS
Show Project Location
Contact Information
TxDOT Contact Gregg Granato, P.E. Phone: (210) 615-6049
Construction Company SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
09/26/2013 11/01/2013 190 201 104.15 % 89.82 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $76,680.09 $312,421.83
Construction $1,661,065.67 $1,480,231.08
Construction EngineeringConstruction Engineering Definition $99,840.61 $71,215.37
Contingency Contingency Definition $20,187.21
Indirect Indirect Definition $79,809.89
Total Cost $1,937,583.47 $1,863,868.28