Proposition 12 v2 Project Detail

Data updated on: 8/01/2014 2:38 PM Print This Page
Project Summary
Project ID 001610022 TxDOT District San Antonio County Name Comal Funding Status Funded
Highway BS 46-C Project Length .324 Miles Project Type Proposition 12 v2 Bid Date 2012-Aug
Work From IN NEW BRAUNFELS FROM KESSLER ST Low Bid Amount $9,677,386.78
Work To HAMPE ST AT UP RR
Description WIDEN ROADWAY
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Gregg Granato, P.E. Phone: (210) 615-6049
Construction Company AUSTIN BRIDGE & ROAD, LP
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
11/09/2012 01/07/2013 243 284 93.11 % 93.44 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $474,191.95 $2,079,147.56
Construction $9,375,373.32 $10,015,789.11
Construction EngineeringConstruction Engineering Definition $479,998.38 $430,798.39
Contingency Contingency Definition $192,580.00
Indirect Indirect Definition $662,900.99
Total Cost $11,185,044.64 $12,525,735.06