Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
001501229 |
TxDOT District |
Waco |
County Name |
McLennan |
Funding Status |
Funded |
| Highway |
IH 35 |
Project Length |
.835 Miles |
Project Type |
Proposition 12 v2 |
District Est. Bid Date |
2013-Jul |
| Work From |
MARTIN LUTHER KING BLVD |
|
|
| Work To |
BU 77 |
| Description |
CONSTRUCT FRONTAGE ROADS |
| Project Note |
This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources. |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Andy Petter, P.E. |
Phone: |
(254) 867-2740 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
08/2012 |
11/2012 |
02/2013 |
05/2013 |
08/2012 |
04/2013 |
02/2013 |
04/2013 |
| Actual Date |
02/2013 |
02/2013 |
03/2013 |
03/2013 |
|
03/2013 |
03/2013 |
03/2013 |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$1,058,865.34 |
$95,648.50 |
| Construction |
$21,609,496.69 |
$0.00 |
Construction Engineering |
$1,043,036.22 |
$0.00 |
Contingency
 |
$32,392.64 |
|
Indirect
 |
$937,852.16 |
|
| Total Cost |
$24,681,643.05 |
$95,648.50 |
|
 |