Proposition 12 v2 Project Detail

Data updated on: 6/03/2013 7:32 AM Print This Page
Project Summary
Project ID 001501229 TxDOT District Waco County Name McLennan Funding Status Funded
Highway IH 35 Project Length .835 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Jul
Work From MARTIN LUTHER KING BLVD
Work To BU 77
Description CONSTRUCT FRONTAGE ROADS
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Andy Petter, P.E. Phone: (254) 867-2740
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 08/2012 11/2012 02/2013 05/2013 08/2012 04/2013 02/2013 04/2013
Actual Date 02/2013 02/2013 03/2013 03/2013 03/2013 03/2013 03/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,058,865.34 $95,648.50
Construction $21,609,496.69 $0.00
Construction EngineeringConstruction Engineering Definition $1,043,036.22 $0.00
Contingency Contingency Definition $32,392.64
Indirect Indirect Definition $937,852.16
Total Cost $24,681,643.05 $95,648.50