Project Summary
Project ID 001501229 TxDOT District Waco County Name McLennan Funding Status Funded
Highway IH 35 Project Length .760 Miles Project Type Proposition 12 v2 Bid Date 2014-Mar
Work From MARTIN LUTHER KING BLVD Low Bid Amount $26,959,896.77
Work To BU 77
Description CONSTRUCT FRONTAGE ROADS
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Andy Petter, P.E. Phone: (254) 867-2740
Construction Company JAMES CONSTRUCTION GROUP, L.L.C.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
05/20/2014 459 0 0.00 % 0.52 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,267,488.54 $782,948.39
Construction $23,072,785.59 $159,302.81
Construction EngineeringConstruction Engineering Definition $1,225,871.16 $4,511.53
Contingency Contingency Definition $40,070.21
Indirect Indirect Definition $1,302,163.01
Total Cost $26,908,378.51 $946,762.73