Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
001308127 |
TxDOT District |
Fort Worth |
County Name |
Wise |
Funding Status |
Funded |
| Highway |
US 81 |
Project Length |
2.105 Miles |
Project Type |
Proposition 12 v2 |
District Est. Bid Date |
2013-Aug |
| Work From |
US 81/@BU 81-SOUTH SIDE DECATUR |
|
|
| Work To |
US 81/@BU 81-SOUTH SIDE DECATUR |
| Description |
CONSTRUCT OVERPASS/UNDERPASS |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Scot D. Smith, P.E. |
Phone: |
(817) 370-6673 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
11/2011 |
08/2012 |
11/2012 |
05/2013 |
04/2013 |
04/2013 |
04/2013 |
04/2013 |
| Actual Date |
11/2011 |
11/2012 |
03/2013 |
|
|
04/2013 |
04/2013 |
|
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$700,939.56 |
$1,075,757.71 |
| Construction |
$14,304,888.95 |
$0.00 |
Construction Engineering |
$856,862.85 |
$0.00 |
Contingency
 |
$371,927.11 |
|
Indirect
 |
$613,679.74 |
|
| Total Cost |
$16,848,298.21 |
$1,075,757.71 |
|
 |