Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 001308127 TxDOT District Fort Worth County Name Wise Funding Status Funded
Highway US 81 Project Length 2.105 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Aug
Work From US 81/@BU 81-SOUTH SIDE DECATUR
Work To US 81/@BU 81-SOUTH SIDE DECATUR
Description CONSTRUCT OVERPASS/UNDERPASS
Show Project Location
Contact Information
TxDOT Contact Scot D. Smith, P.E. Phone: (817) 370-6673
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 11/2011 08/2012 11/2012 05/2013 04/2013 04/2013 04/2013 04/2013
Actual Date 11/2011 11/2012 03/2013 04/2013 04/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $700,939.56 $1,075,757.71
Construction $14,304,888.95 $0.00
Construction EngineeringConstruction Engineering Definition $856,862.85 $0.00
Contingency Contingency Definition $371,927.11
Indirect Indirect Definition $613,679.74
Total Cost $16,848,298.21 $1,075,757.71