Proposition 12 v2 Project Detail

Data updated on: 11/10/2014 3:25 PM Print This Page
Project Summary
Project ID 000912078 TxDOT District Dallas County Name Rockwall Funding Status Funded
Highway IH 30 Project Length 2.572 Miles Project Type Proposition 12 v2 Bid Date 2013-Jul
Work From AT FM 551 Low Bid Amount $30,862,690.37
Work To .
Description CONSTRUCT OVERPASS/UNDERPASS
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Maher Ghanayem, P.E. Phone: (214) 320-6691
Construction Company WEBBER, LLC
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
12/10/2013 06/10/2014 505 99 19.60 % 12.51 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,512,271.83 $182,876.55
Construction $27,483,177.90 $4,031,353.87
Construction EngineeringConstruction Engineering Definition $1,447,460.18 $65,117.65
Contingency Contingency Definition $922,794.44
Indirect Indirect Definition $1,345,613.30
Total Cost $32,711,317.65 $4,279,348.07