Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 000912078 TxDOT District Dallas County Name Rockwall Funding Status Funded
Highway IH 30 Project Length 2.572 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Jul
Work From AT FM 551
Work To .
Description CONSTRUCT OVERPASS/UNDERPASS
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Mo Bur, P.E. Phone: (214) 320-6281
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 08/2011 09/2011 05/2012 04/2013 05/2012 03/2013 04/2013 04/2013
Actual Date 08/2011 09/2011 03/2013 04/2013 04/2013 04/2013 04/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,445,663.81 $119,412.97
Construction $29,503,343.10 $0.00
Construction EngineeringConstruction Engineering Definition $1,383,706.79 $0.00
Contingency Contingency Definition $882,149.96
Indirect Indirect Definition $1,286,345.76
Total Cost $34,501,209.42 $119,412.97