Proposition 12 v2 Project Detail

Data updated on: 12/02/2014 8:49 AM Print This Page
Project Summary
Project ID 000606093 TxDOT District Abilene County Name Taylor Funding Status Funded
Highway IH 20 Project Length 3.961 Miles Project Type Proposition 12 v2 Bid Date 2012-Jun
Work From PINE STREET Low Bid Amount $12,481,302.24
Work To LP 322__(FRONTAGE ROADS ONLY)
Description CONSTRUCT FREEWAY RAMPS
Show Project Location
Contact Information
TxDOT Contact Blair Haynie, P.E. Phone: (325) 676-6810
Construction Company J. H. STRAIN & SONS, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
08/28/2012 10/25/2012 416 409 98.32 % 98.97 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $611,583.81 $614,901.31
Construction $11,294,700.35 $13,081,307.05
Construction EngineeringConstruction Engineering Definition $847,480.42 $493,647.67
Contingency Contingency Definition $262,107.35
Indirect Indirect Definition $1,268,100.31
Total Cost $14,283,972.24 $14,189,856.03