Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
000514077 |
TxDOT District |
Odessa |
County Name |
Midland |
Funding Status |
Funded |
| Highway |
IH 20 |
Project Length |
14.694 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Jun |
| Work From |
0.4 MI EAST OF SH 349 |
Low Bid Amount |
$10,773,473.14 |
| Work To |
ECTOR COUNTY LINE |
| Description |
REPAIR ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Gary J. Law, P.E. |
Phone: |
(432) 332-0501 |
| Construction Company |
JONES BROS. DIRT & PAVING CONTRACTORS, INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
|
|
|
|
|
|
|
|
| Actual Date |
12/2010 |
02/2011 |
04/2011 |
11/2011 |
03/2011 |
|
|
11/2011 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 08/20/2012 |
04/08/2013 |
120 |
40 |
33.33 % |
8.79 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$527,900.18 |
$52,764.17 |
| Construction |
$10,092,001.50 |
$960,208.91 |
Construction Engineering |
$645,331.04 |
$46,606.52 |
Contingency
 |
$280,110.30 |
|
Indirect
 |
$1,329,446.59 |
|
| Total Cost |
$12,874,789.61 |
$1,059,579.60 |
|
 |