Proposition 12 v2 Project Detail

Data updated on: 6/03/2013 7:32 AM Print This Page
Project Summary
Project ID 000514077 TxDOT District Odessa County Name Midland Funding Status Funded
Highway IH 20 Project Length 14.694 Miles Project Type Proposition 12 v2 Bid Date 2012-Jun
Work From 0.4 MI EAST OF SH 349 Low Bid Amount $10,773,473.14
Work To ECTOR COUNTY LINE
Description REPAIR ROADWAY
Show Project Location
Contact Information
TxDOT Contact Gary J. Law, P.E. Phone: (432) 332-0501
Construction Company JONES BROS. DIRT & PAVING CONTRACTORS, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
08/20/2012 04/08/2013 120 40 33.33 % 8.79 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $527,900.18 $52,764.17
Construction $10,092,001.50 $960,208.91
Construction EngineeringConstruction Engineering Definition $645,331.04 $46,606.52
Contingency Contingency Definition $280,110.30
Indirect Indirect Definition $1,329,446.59
Total Cost $12,874,789.61 $1,059,579.60