Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 000505102 TxDOT District Abilene County Name Howard Funding Status Funded
Highway IH 20 Project Length 2.719 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-May
Work From AT US 87 (NEW LOCATION)
Work To .
Description CONSTRUCT INTERCHANGE
Show Project Location
Contact Information
TxDOT Contact Blair Haynie, P.E. Phone: (325) 676-6810
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 09/2011 03/2012 09/2012 04/2013 09/2011 04/2013 04/2013 04/2013
Actual Date 08/2011 02/2012 04/2012 01/2013 01/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $914,719.43 $998,788.88
Construction $18,667,743.52 $0.00
Construction EngineeringConstruction Engineering Definition $875,517.17 $0.00
Contingency Contingency Definition $558,165.53
Indirect Indirect Definition $1,596,092.07
Total Cost $22,612,237.72 $998,788.88