Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
000505102 |
TxDOT District |
Abilene |
County Name |
Howard |
Funding Status |
Funded |
| Highway |
IH 20 |
Project Length |
2.719 Miles |
Project Type |
Proposition 12 v2 |
District Est. Bid Date |
2013-May |
| Work From |
AT US 87 (NEW LOCATION) |
|
|
| Work To |
. |
| Description |
CONSTRUCT INTERCHANGE |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Blair Haynie, P.E. |
Phone: |
(325) 676-6810 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
09/2011 |
03/2012 |
09/2012 |
04/2013 |
09/2011 |
04/2013 |
04/2013 |
04/2013 |
| Actual Date |
08/2011 |
02/2012 |
04/2012 |
01/2013 |
01/2013 |
|
|
|
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$914,719.43 |
$998,788.88 |
| Construction |
$18,667,743.52 |
$0.00 |
Construction Engineering |
$875,517.17 |
$0.00 |
Contingency
 |
$558,165.53 |
|
Indirect
 |
$1,596,092.07 |
|
| Total Cost |
$22,612,237.72 |
$998,788.88 |
|
 |