Proposition 12 v2 Project Detail

Data updated on: 9/02/2014 11:01AM Print This Page
Project Summary
Project ID 000201090 TxDOT District El Paso County Name El Paso Funding Status Funded
Highway SH 20 Project Length .700 Miles Project Type Proposition 12 v2 Bid Date 2013-Aug
Work From CONCEPCION ST Low Bid Amount $10,475,334.54
Work To GLENWOOD ST
Description REPAIR ROADWAY
Show Project Location
Contact Information
TxDOT Contact Celia Salazar, P.E. Phone: (915)-790-4400
Construction Company JORDAN FOSTER CONSTRUCTION, LLC
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
01/06/2014 01/20/2014 280 132 47.14 % 52.58 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $478,657.39 $1,138,488.61
Construction $9,041,089.06 $5,391,409.02
Construction EngineeringConstruction Engineering Definition $478,657.39 $136,965.83
Contingency Contingency Definition $4,884.26
Indirect Indirect Definition $766,828.68
Total Cost $10,770,116.78 $6,666,863.46