Proposition 12 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
800015015 |
TxDOT District |
San Antonio |
County Name |
Bexar |
Funding Status |
Funded |
| Highway |
MH |
Project Length |
1.679 Miles |
Project Type |
Proposition 12 |
Bid Date |
2011-Apr |
| Work From |
WURZBACH PARKWAY ON NEW LOCATION |
Low Bid Amount |
$49,434,317.59 |
| Work To |
WEST AVE TO JONES MALTSBERGER |
| Description |
CONSTRUCT NEW ROAD |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Gregg Granato, P.E. |
Phone: |
(210) 615-6049 |
| Construction Company |
WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
06/2010 |
09/2010 |
02/2011 |
07/2011 |
08/2011 |
07/2011 |
08/2011 |
08/2011 |
| Actual Date |
03/2010 |
07/2010 |
09/2010 |
02/2011 |
04/2010 |
12/2010 |
04/2010 |
02/2011 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 06/14/2011 |
07/06/2011 |
1,160 |
512 |
44.14 % |
47.13 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$2,381,136.26 |
$2,655,030.74 |
| Construction |
$59,664,996.54 |
$24,665,163.13 |
Construction Engineering |
$2,203,551.79 |
$1,248,798.22 |
Contingency
 |
$3,401,707.19 |
|
Indirect
 |
$2,802,925.81 |
|
| Total Cost |
$70,454,317.59 |
$28,568,992.09 |
|
 |