Proposition 12 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 255201033 TxDOT District El Paso County Name El Paso Funding Status Funded
Highway LP 375 Project Length 3.624 Miles Project Type Proposition 12 Bid Date 2011-Sep
Work From 0.038 MI W OF IH 10 AT LOOP 375 Low Bid Amount $61,272,749.49
Work To 0.479 MI E OF FRANKLIN MT STATE PRK
Description WIDEN ROADWAY
Show Project Location
Contact Information
TxDOT Contact Celia Salazar, P.E. Phone: (915)-790-4400
Construction Company SUNDT CONSTRUCTION, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
10/27/2011 02/06/2012 696 654 90.71 % 88.65 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $3,002,364.73 $7,429,588.12
Construction $67,760,553.38 $65,869,775.75
Construction EngineeringConstruction Engineering Definition $2,910,455.60 $1,224,992.10
Contingency Contingency Definition $1,691,127.89
Indirect Indirect Definition $7,720,366.44
Total Cost $83,084,868.04 $74,524,355.97