Proposition 12 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 213904020 TxDOT District Paris County Name Hunt Funding Status Funded
Highway SH 11 Project Length 12.996 Miles Project Type Proposition 12 Bid Date 2011-Mar
Work From SH 34 Low Bid Amount $6,435,254.20
Work To SH 224
Description REPAIR ROADWAY
Show Project Location
Contact Information
TxDOT Contact Rick Mackey, P.E. Phone: (903) 737-9375
Construction Company D. L. LENNON INCORPORATED - CONTRACTOR
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
04/18/2011 07/18/2011 336 338 96.30 % 101.13 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $315,327.46 $108,499.80
Construction $5,973,839.39 $7,954,378.63
Construction EngineeringConstruction Engineering Definition $450,467.79 $175,884.87
Contingency Contingency Definition $418,291.52
Indirect Indirect Definition $400,916.34
Total Cost $7,558,842.50 $8,238,763.30