Proposition 12 Project Detail

Data updated on: 10/01/2014 8:23 AM Print This Page
Project Summary
Project ID 212103151 TxDOT District El Paso County Name El Paso Funding Status Funded
Highway IH 10 Project Length 4.608 Miles Project Type Traditional Bid Date 2014-Jul
Work From VISCOUNT BLVD. Low Bid Amount $18,068,661.12
Work To FM 659 (ZARAGOZA ROAD)
Description CONSTRUCT NEW ROADWAY LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Celia Salazar, P.E. Phone: (915)-790-4400
Construction Company DAN WILLIAMS COMPANY
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
09/09/2014 09/22/2014 316 5 1.58 % 7.10 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $885,364.39 $864,720.92
Construction $20,134,094.45 $0.00
Construction EngineeringConstruction Engineering Definition $885,364.39 $935.13
Contingency Contingency Definition $9,034.33
Indirect Indirect Definition $872,716.33
Total Cost $22,786,573.89 $865,656.05