Proposition 12 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
113602046 |
TxDOT District |
Pharr |
County Name |
Cameron |
Funding Status |
Funded |
| Highway |
FM 800 |
Project Length |
1.295 Miles |
Project Type |
Proposition 12 |
Bid Date |
2010-Sep |
| Work From |
0.54 MI SOUTH OF BUS 83 |
Low Bid Amount |
$5,263,323.45 |
| Work To |
TRIMPE LANE |
| Description |
INSTALL/UPGRADE DRAINAGE STRUCTURES |
| Project Note |
This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources. |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Homero Bazan, P.E. |
Phone: |
(956) 702-6214 |
| Construction Company |
LEAL CONSTRUCTION, INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
01/2010 |
01/2010 |
02/2010 |
03/2010 |
03/2010 |
05/2010 |
02/2010 |
05/2010 |
| Actual Date |
04/2010 |
04/2010 |
04/2010 |
04/2010 |
08/2010 |
06/2010 |
06/2010 |
09/2010 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 10/20/2010 |
11/15/2010 |
264 |
309 |
117.05 % |
93.39 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$270,214.43 |
$352,526.55 |
| Construction |
$5,571,833.28 |
$5,535,389.28 |
Construction Engineering |
$275,729.01 |
$392,003.65 |
Contingency
 |
$358,447.71 |
|
Indirect
 |
$361,590.32 |
|
| Total Cost |
$6,837,814.75 |
$6,279,919.48 |
|
 |